Goal To identify planning requirements and any necessary upgrades to the transmission and distribution networks, with a view to drawing up the PDIRG 2028–2037 proposal

Target Developers of projects for the production of renewable or low-carbon gases, with the aim of injecting such gas into the Public Gas Network
Public consultation

Injection of Renewable Gases into the Public Gas Network

As part of the preparation of the RNTIAT Development and Investment Plan for the period 2028–2037 (PDIRG 2028–2037), in particular for the purpose of submitting a proposal to the Directorate-General for Energy and Geology (DGEG) and to the Energy Services Regulatory Authority (ERSE) by 31 March 2027, in accordance with the provisions of the applicable legislation and regulations, namely Article 87(1) of Decree-Law No. 62/2020 of 28 August (current version), and in compliance with ERSE’s recommendations regarding the previous PDIRG 2026 –2035, all developers of renewable or low-carbon gas production projects aiming to inject such gas into the Public Gas Network (RPG) are hereby informed that REN Gasodutos, S.A., in its capacity as Gas Transmission Network Operator and the entity responsible for the Overall Technical Management of the gas system, in coordination with the Distribution Network Operators, will launch a public consultation to run from 26 October to 25 November 2026 with the aim of identifying potential planning requirements for consideration in the next edition of the PDIRG 2028–2037.

This consultation serves as a tool which, not only contributes to the proper planning of the National Gas Transmission Network and the scheduling of investments in the context of injecting renewable gases into the RPG, but also aims to identify potential requirements for reinforcing this infrastructure at the interface between the transmission and distribution networks, with the aim of identifying potential network reinforcement requirements arising from the possible connection of renewable gas production projects to the RPG.

How can I take part in this public consultation?

To take part in the consultation, project developers must:

  1. Complete the questionnaire available for download herewith details of the generation project. One questionnaire must be submitted per project;
  2. Submit the completed questionnaire by 25 November 2026, to consultamercadogr@ren.pt, and notify the distribution network operator where the renewable gas is to be injected into the RPG by email: