REN informs that, at 10:00 p.m., it had already managed to power on 85 of 89 substations and cut-off stations, as part of the operation to re-energize the national electricity system, affected by this morning's blackout.
The substations of Trafaria, Divor, Estremoz and Portimão are still unable to receive energy, a situation that REN hopes to solve today. The most densely populated areas still affected are Almada Oeste and the city of Portimão.
At this point, about 2.5 million consumers are already connected to the network.