(referring to Article 20(1) of Decree-Law No. 80/2023, dated September 6th)
Unused allocated capacity | Connections to the National Transmission Network
In compliance with Article 2(11) of Directive No. 20-A/2023, dated December 29th, from the Regulatory Entity for Energy Services, it is hereby disclosed that the unused allocated capacity, determined in accordance with Article 4(4) of Decree-Law No. 80/2023, dated September 6th, concerning consumption facilities in the Sines High Demand Zone with an assigned interconnection point on the National Transmission Network at very high voltage, is 1,316 MVA.
It is hereby informed that the owners of the mentioned consumption facilities will be notified in accordance with paragraph 2 of Article 8 of the aforementioned Decree-Law.